Sewer Project Updates

Updated: January 30, 2008
Current Projects
- Firestone Dr. will have 2 sections of sanitary sewer
line repaired. First will be at the corner of Firestone Dr. and Pomona
Dr. going north on Firestone Dr. for one section of sewer line. This
project will start (weather permitting) January 31, 2008 and will take
approximately 1 week. The second repair on Firestone Dr. will begin
at the intersection of Firestone Dr. and Lake Valley Dr. going north
on Firestone Dr. This project will take approximately 2 weeks. All affected
residents have been notified. If you have any specific needs please
let the Bostwick Excavating foreman on site know and they will work
to address your issues.
- Pomona Dr. at Firestone Dr. starting at Firestone
Dr. going east on Pomona Dr. for one section of sanitary sewer line.
This project will take approximately 2 weeks. All affected residents
have been notified.
Landscape/Lawn Restoration Projects
- During winter all restoration will be rough only. Final restoration
will be when the ground dries. Restoration projects will be completed
in the order they were excavated.
- Restoration of Garnet & Moffett Dr. will be completed
after the Spring thaw.
- Restoration of Crystal Pte projects will be completed
after the Spring thaw.
General Notes
- Sewer project start dates are weather permitting and assuming no other
sewer emergency situations arise.
- Restorations of all projects will commence once the ground has had
time to settle and in the order which they were completed.
For more information, contact Penelope Sharich, Sewer Department Coordinator,
at (810) 629-1537 or by email at psharich@fentontownship.org.
|