- North Rd. excavation from the pump station south 250 ft. will begin
Tuesday August 25th, weather permitting, and will take approximately
one week.
- Dalhart pipe patching will take place the week of August 24th.
- Video/Cleaning project is on-going through September in specified
areas, call the Township for details.
- Painting of pump stations is almost complete. There are still two
stations that need to be completely painted both inside and outside.
- Rehabilitation of Pump Station #44 in Chateaux Du Lac will begin in
early September.
Landscape/Lawn Restoration Projects
- All restoration and landscaping from previous projects is completed.
General Notes
- Sewer project start dates are weather permitting and assuming no other
sewer emergency situations arise.
- Restorations of all projects will commence once the ground has had
time to settle and in the order which they were completed.
For more information, contact Penelope Sharich, Sewer Department Coordinator,